Floor, Door, and Nav Table
Phin Sprague, Jr. --
"Elsewhere on the boat the Caprails are being
installed. The Bottom is being faired and is scheduled to be painted the
week of June 16th. The engine box is being completed. The doors, door
frames, cabinet doors and frames are getting the second to last coat of
varnish. The booms are being painted. The dolphin striker and whisker
stay spreaders are almost finished. The boom gallows is being designed.
The travelers are about to be started, the turnbuckles and stanchions
have arrived. The computer is being built. The electrical panels are being
built. The blocks are being built. The corian counters are scheduled for
delivery next week. The shower pans are ready for gelcoating. We have
extended the boat ramp in preparation for launching. "
 |
 |
Hanging doors and fitting floors.
Christian is working on the doors, while Steve's on floors. |
 |
 |
| Electrical closet: Mike has installed the DC portion
of the wiring in the port electrical closet. |
Mike wiring anchor pressure washer in chain locker. |
 |
| Nav station first fitting. Peter has roughed out the
nav station and now it is being fitted to make sure that all of the
issues are addressed. |
|