Floor, Door, and Nav Table

Phin Sprague, Jr. --

"Elsewhere on the boat the Caprails are being installed. The Bottom is being faired and is scheduled to be painted the week of June 16th. The engine box is being completed. The doors, door frames, cabinet doors and frames are getting the second to last coat of varnish. The booms are being painted. The dolphin striker and whisker stay spreaders are almost finished. The boom gallows is being designed. The travelers are about to be started, the turnbuckles and stanchions have arrived. The computer is being built. The electrical panels are being built. The blocks are being built. The corian counters are scheduled for delivery next week. The shower pans are ready for gelcoating. We have extended the boat ramp in preparation for launching. "

Hanging doors and fitting floors.
Christian is working on the doors, while Steve's on floors.
Electrical closet: Mike has installed the DC portion of the wiring in the port electrical closet. Mike wiring anchor pressure washer in chain locker.
Nav station first fitting. Peter has roughed out the nav station and now it is being fitted to make sure that all of the issues are addressed.